Summer Street Pavement Rehabilitation to Begin
Summer Street Pavement Rehabilitation will begin the first week of June

Summer Street Pavement Rehabilitation to begin the first week of June

The drainage work on Summer Street has been completed and the pavement reclamation, grading and paving work will commence the first week of June.  During this time the pavement will be ground up, reshaped and paved between Heath Road and Jim's Service Center as Phase 1, it is anticipated this work will occur between June 5th and June the 20th.  A second phase from Jim's Service Center to Sea Road will follow immediately and the same process will ensue and extend into mid July.

The work is weather dependent and will be scheduled to minimize impacts as much as possible.  Motorists are asked to proceed with caution and expect delays.  Please plan accordingly and remember to be safe while traveling through a work zone.