Jun 19

Ross Road Utility Work

Posted on June 19, 2019 at 9:55 AM by Karen Winton

Ross Road
Ross Road Primary Line Replacement
Kennebunk Light & Power is undertaking a facility upgrade to its infrastructure along the Ross Road corridor. This project began in early May with the setting of new poles and tree trimming work. 

The transfer of wires and replacement of core components will be ongoing over the next 12 week period. Kennebunk Light & Power has contracted much of this work, but any questions should be directed to the District Monday through Friday, between 8:00 a.m. and 5:00 p.m. at 985-3311 or via email.

This project will assist in system performance and reliability and will align with the Town’s plan to rehabilitate Ross Road as part of a State funded Municipal Partnership Initiative grant from the Maine DOT in 2020. 

Please remember that this project will be an active construction zone and motorists should expect delays and be extra attentive when traveling through a work zone.

Stay Informed
You can sign up to receive email notifications from Kennebunk Light & Power here, or from the Town of Kennebunk here.
Sep 21

Summer Street Rehabilitation Project - WIN 21928.05 - September Update

Posted on September 21, 2018 at 2:14 PM by Christopher Osterrieder

Much of the design work of the project was completed in July of 2018.  Plans were posted for public review and comment in early August and utility coordination has been undertaken.  Utility coordination primarily involves relocation of overhead utilities.  Key milestones looking ahead include:

  • Placement of new utility poles (late September 2018 - mid November 2018) - Kennebunk Light & Power
  • Transfer of overhead utilities to new poles (October 2018 - April 2019) - Kennebunk Light & Power; Consolidated Communications; Spectrum (Cable)
  • Drainage work (Late October - March 2019) - work is likely to extend into winter - BREX Corp.
  • Roadway Rehabilitation April 2019 - June 2019
    • Pavement Reclamation
    • fine grading of new roadway profile
    • placement of binder pavement
    • granite curb installation
    • sidewalk construction
    • surface pavement
    • signage installation
    • loam, seed & mulch
    • project striping
Any questions related to the project may be directed to the Town Engineer Chris Osterrieder.